September 10-  Foundation walls are unveiled.  And the rough ins for the basement bathroom are in.  We are not finishing this bathroom, but we wanted to put in rough ins in case we want to add one in the future.   Sump pit and the water supply line which we will go to the well.  Progress is being made, unfortunately we also take a step back.  The concrete guys were unfamiliar with the drain tile/forms used for the foundation and they took them out with the forms.  So the drain tiles will have to be reinstalled.   Oh, well.